Category Archives: Chamblee High School

Jester Community Town Hall

I’m inviting all students, parents, teachers, and the community at large to my upcoming Community Town Hall meetings.

DUNWOODY
When: May 14th @ 7pm
Where: St. Luke’s – 1978 Mt Vernon Rd, Dunwoody
Room: Chapel – From the Manhasset entrance, turn right in the lobby

CHAMBLEE
Date/time: TBD
Where: Chamblee Library

As we approach the end of the 2018-2019 school year, we have a lot to talk about. No speeches here … let’s discuss what’s going on. What’s going on? Off the top of my head, E-SPLOST projects are running out of money, the school district is squeezing more and more children into our schools and the school district will be asking for a loan of up to $250 million soon. Furthermore, the Dunwoody, Chamblee, Brookhaven and Doraville areas will see some redistricting over the next few years as new schools come online.

Come one, come all. I will also invite various representatives from our other local governments to join us.

See you soon.

Architect’s Preliminary Report Chamblee Charter HS Building Additions

Hussey Gay Bell (HGB) is the Architectural and Engineering (A&E) firm hired to construct a 600-seat, three-story addition to Chamblee Charter High School (CCHS). This week they came out with a preliminary report. No way around it, this project is going way over budget.

  Chamblee Charter High School – Preliminary Report – January 24, 2019
  2018-10 CCHS proposed addition schemes
  1/30 CAC Presentation
  Traffic Impact Study

PARKING
If the building additions at CCHS happen, it doesn’t look like there will be any additional parking.

The last Hussey Gay Bell report provided two options: 1) Buy adjacent land or 2) Build a parking garage where the field is and put a field on top of the parking garage.

In this latest report, HGB noted the following:

1. The Original CCHS Feasibility Study (that we based our vote off of) proposed turning the existing parking lot into a multi level parking garage. HGB notes an existing below-grade storm water retention structure under the parking lot. HGB is “concerned that the impact of relocating this structure and associated costs may not be accommodated by the existing SCL of $17.2 million and we do not consider this a viable option.”

2. HGB has confirmed that the city ordinances will not allow for the proposed 116 parking spaces in front of the school along Chamblee Dunwoody Rd.

3. Given the lack of parking spaces along Chamblee Dunwoody Rd, the parking garage where the field is will have to be even larger than anticipated. I don’t see how we can stay under budget and put a field on top of a parking garage.

4. I don’t see any mention of buying land adjacent to the school, so I guess that’s out. The money to purchase land was never in the budget anyway.

Escalating construction costs
The Stated Cost Limitation (SCL) for the project is $17,232,000.00. Escalating construction costs and their impact on the SCL, “we anticipate costs will exceed the SCL.” says HGB.


Construction Advisory Committee

Dear CCHS Community,

Please attend the Construction Advisory Committee (CAC) meeting tomorrow, January 30, 2019 at 6pm in the CCHS auditorium.

The Preliminary Architect Report for the 600 seat addition to Chamblee Charter High School is now posted on the CCHS Governing Board website along with drawings. The date of the report is listed as October 24, 2018 with an amendment dated January 24, 2019.

The links are below:

Plans: https://docs.google.com/viewer?a=v&pid=sites&srcid=ZGVmYXVsdGRvbWFpbnxjaGFtYmxlZWNoYXJ0ZXJnYnxneDoxODMwODA5Mjc0ODBkZjI3

Architect’s Report: https://docs.google.com/viewer?a=v&pid=sites&srcid=ZGVmYXVsdGRvbWFpbnxjaGFtYmxlZWNoYXJ0ZXJnYnxneDo0MjdjMDdiYjkyMTkxMWUz

In a nutshell, the 600 seat addition will be located near the corner of Chamblee-Dunwoody Road and Mendenhall Street. A parking deck will be built where the practice field is and an elevated turfed practice field will be built above it. The report identifies items that may give concern about staying within the budget. These may be ordinary concerns common at this stage of design, or not.

If possible, please share these documents with your constituencies.


Related Posts

Chamblee Cluster 7-Year Enrollment Forecasts
January 19, 2019 – Chamblee Charter High School is currently right at capacity with 1,722 students enrolled. Chamblee Charter HS is currently projected to have 1979 students by 2025.

Is 600 More Seats At Chamblee Charter HS A Good Idea?
January 17, 2017 – Please help me understand why adding 600 seats to Chamblee Charter High School is good for anybody in that community? I suspect that any support is driven by redistricting.

Pros and Cons of adding 600 seats to Dunwoody HS
January 7, 2017 – Moving forward, I’m trying to understand the support for the building addition at Dunwoody High School. The speculation that some Dunwoody residents would be redistricted out of DHS seems to be the only reason for any continued support of the building additions.

Chamblee Charter High School – 600 Seat Addition
November 2, 2016 – The recommendation to construct a600-seat, three-story addition to Chamblee Charter High School. The project will also include…
.
 

Dunwoody High School – 600 Seat Addition
November 2, 2016 – The recommendation to construct a 600-seat, 29-classroom, two-story addition to Dunwoody High School. The project will also include…

Lakeside High School – 750 Seat Addition
November 2, 2016 – The recommendation to construct a 750-seat, 38-classroom, two-story addition to Lakeside High School. The project will also include…