Category Archives: SPLOST

Dunwoody HS Trailer Park

Dunwoody High School (DHS) will be a trailer park until at least 2022. This Summer a new 4 classroom quad with bathrooms will be placed next to the picnic tables. Over the next couple years, 2 more 4-classroom quads are expected to be placed next to the quad going in this Summer. If all E-SPLOST projects are on time and budget, the permanent classroom additions are expected to be completed in 2022.

The School District will first have to get land disturbance permits from the City of Dunwoody before installing these new mobile quad classrooms. It is undetermined if the school district will seek waivers to the City of Dunwoody’s ordinances forbidding cutting down trees and/or having temporary structures. It is also unknown what will be done with the trailer park once the trailers are eventually removed.
PROJECTIONS
Last year the school district underestimated enrollment for this academic year. The school district estimated that the Fall 2018 enrollment at DHS would be 1,941 and Fall 2019 enrollment would be 1,977. The district estimated 2,093 students at DHS by 2022.
ACTUALS
Official enrollment at DHS is currently 1,982 students. A large class is expected to come up from Peachtree Charter Middle School (PCMS) causing enrollment to increase to a now estimated 2042.
At the DHS council meeting yesterday, central office staff mentioned they expect enrollment to peak at DHS next year. When questioned about trailers at PCMS, Central Staff noted that they were increasing the number of trailers at the middle school next year. I don’t understand how enrollment will peak next year for DHS while at the same time they adding more trailers at the middle school.
MOVING FORWARD
It is reasonable to expect the number of students at DHS to continue to swell and squeezed like sardines into a school and campus originally designed for about 1500 students. The addition that is planned wont’ be completed until 2022 IF COMPLETED ON SCHEDULE. There are thousands of empty seats across the school district. The overcrowding at Dunwoody, Chamblee Charter, and Lakeside High Schools could be fixed tomorrow by redistricting.

Building Additions – Project Plan and Schedule

The SPLOST V building additions at Lakeside HS (LHS), Chamblee Charter HS (CCHS) and Dunwoody HS (DHS) will be “classroom additions and necessary core space additions and/or parking spaces”. But what does that really mean?

BUILDING ADDITIONS – PROJECT LIST
I met with Joshua Williams, the Chief Operating Officer, and the other board members on Monday. The building additions project includes the following:
* Classroom additions
* Kitchen extension
* Cafeteria extension
* New/extended media center addition
* New parking
RENOVATIONS
Each building addition project has a specific budget. Whatever money is left over from the building additions, will go into the district wide E-SPLOST Contingency Fund. There will absolutely not be any renovations done to other areas of the school with building additions budget unless they are impacted by the original projects.
BUILDING ADDITIONS & FIELD RENOVATIONS – SCHEDULE
In March 2017, the board and administration passed a schedule for all E-SPLOST V projects. That schedule has not changed. At DHS, engineers are looking into the possibility of separating out the field renovations project and doing that early.

Project Description Budget Anticipated Overall Start Date Anticipated Construction Start Date Anticipated Construction Finish Date Anticipated Overall Finish Date
Chamblee HS 30-classroom addition $21,540,000 Mar. 2017 Nov. 2018 Jul. 2020 Oct. 2020
New Cross Keys HS New 119-classroom high school $84,800,000 Aug. 2017 Sep. 2019 Sep. 2021 Jun. 2022
Lakeside HS 38-classroom addition and synthetic turf installation $26,990,000 Nov. 2018 Jul. 2020 Mar. 2022 Jun. 2022
Dunwoody HS 26-classroom addition and synthetic turf installation $17,690,000 Feb. 2019 Oct. 2020 Jun. 2022 Sep. 2022
Peachtree MS 26-classroom addition $14,100,000 Oct. 2019 Jun. 2021 Feb. 2023 May. 2023

NEW CROSS KEYS / BROOKHAVEN HIGH SCHOOL
$85 million was budgeted for a New Cross Keys HS at the former Briarcliff HS site (or cost-neutral alternative site). A majority of the new Cross Keys High School population will live West of I-85 plus students from Sagamore and/or perhaps Oak Grove. The current Briarcliff HS site is East of I-85 on Druid Hills Rd and sits on 17.6 acres.
FIELD RENOVATIONS
E-SPLOST V also includes artificial turf installation at 19 high schools. At LHS and DHS, the turf installation will happen at the same time as the building additions.