Administrators were met with a full house on Tuesday when presenting proposals to address over-capacity issues in the Cross Keys Cluster. Another community meeting will be held tonight – Thu, Sep 17th at 6 PM, Sequoyah MS.
The Cross Keys cluster consists of 4 elementary schools, a middle school and high school. To serve the growing student population, 18 portable classrooms were added this year to the elementary schools and 16 portable classrooms were added to the middle and high school.
School | New Trailers This Year |
Total Classrooms In Trailers |
---|---|---|
Cary Reynolds ES | 4 | 25 |
Dresden ES | 12 | 26 |
Montclair ES | 2 | 18 |
Sequoyah MS | 8 | 17 |
Cross Keys HS | 8 | 15 |
The proposed solution is a multi phased approach.
Phase I (Summer 2016) – Phase I will be to relocate DESA, Avondale MS and Warren Tech to less utilized facilities down south. 3rd, 4th and/or 5th grade academies will be created for Cary Reynolds and Dresden in the recently vacated buildings.
Phase II (Fall 2017 and beyond) – Phase II will consist of the construction of two new elementary schools and the development of up to 3 district wide Pre-K centers. Relief for the middle and high schools will be obtained through new school or renovation additions to the existing schools.
Funding – Funding will be through E-SLPOST and COPs (Certificates of Participation), publicly offered or privately placed, both competitively, repaid by E-SPLOST V revenues.
Public meetings: (Stakeholder Engagement)
- Tue, Sep 15th at 6 PM, Cross Keys HS
- Thu, Sep 17th at 6 PM, Sequoyah MS
October 5th Board Meeting:
Allocate $9.25 million of E-SPLOST IV funds for
(1) Improvements at Warren Tech, Terry Mill, & Former ISC,
(2) Modular buildings and parking,
(3) Design of two elementary schools, and
(4) Feasibility study for middle and high school capacity
Approve moving forward with COPS financing package
Proposal to Address Over-Capacity Issues in the Cross Keys Cluster